Date | Responsibility | Deliverables | ||
---|---|---|---|---|
| Authoring begins for the July 2019 International Edition editing cycle. | |||
| Content team (Yongsheng Gao) to deliver final MRCM change requests to EPS Team (Linda Bird) for action | |||
| EPS Team delivers MRCM changes to content team for review - Content Team to complete this by | |||
| Content team (Yongsheng Gao) to deliver final reviewed MRCM changes plus any feedback to Linda Bird EPS Team | |||
| EPS Team to make any necessary changes (based on feedback from the authors) - Linda Bird to complete this ( and verify with Yongsheng Gao) Content Team by | |||
| Jane Millar | Cut off for external collaboration partner CRS Requests (IHE, HL7, etc) - set date of 15th March + 15th September each cycle for clarity | ||
| NO FURTHER MRCM CHANGES ACCEPTED - everyone has agreed this, with the caveat that any critical changes can be reviewed by all of us in order to analyse impact vs business case and allow a change if absolutely necessary. | |||
| Final MRMC refsets delivered by Linda BirdEPS Team to Release Management team for review + MRCM updated in the SCA to ensure remaining new cycle content validated against the latest version. | |||
| SNOMED International | Development Tech Team | (Kai Kewley) to now:
| |
| NO FURTHER CRS REQUESTS ACCEPTED (Single content request cut off) | |||
|
| |||
01 May |
| |||
03 | Content team review, rebase and finalise all content (Maria Braithwaite to manage) | |||
03 | Content team promote to MAIN final content for all projects to be released in the current editing cycle (weekend contingency) - Maria Braithwaite to confirm | |||
07 | Content Release Lead (Maria Braithwaite) to request (via Infra ticket) formal lock down of all Projects (i.e. no promotions allowed), except for the Internal QA Project - which needs to remain open until from CONTENT CUTOFF DATE in order to allow Content Release Lead to promote all final QA fixes before handover. | |||
07 | Final content review (2 days ) - Content Release Lead (Maria Braithwaite) to action- BEWARE OF BANK HOLIDAY ON 6th May 2019!) Review of new observable entity and evaluation procedure concepts for conflicts with the LOINC agreement (Farzaneh Ashrafi Suzanne Santamaria) | |||
09 |
| |||
| Planned Initial Handover meeting | |||
10 termServer branching and Release versioning - SNOMED International Development Team, + |
| |||
| Transition from Stated Relationships to OWL refsets + Validation of the new complete OWL refsets | |||
| termServer branching and Release versioning | |||
| Andrew Atkinson | Full validation of the initial exported content, including the new OWL refsets | ||
|
| |||
|
| |||
|
| |||
|
| |||
Handover of Release Notes to technical team Release manager (Andrew Atkinson) | ||||
| PLANNED Alpha Release date - Release manager (Andrew Atkinson) to implement Restart validation in SCA (no longer relevant - new process should allow validation to re-start immediately when Content authoring starts for next editing cycle) | |||
| PLANNED Alpha feedback deadline | |||
29 May | PLANNED BETA Release date - Release manager (Andrew Atkinson) to implement | |||
07 | PLANNED BETA feedback deadline | |||
| Member Release date - Release manager (Andrew Atkinson) to implement | |||
| Public Release date - Release manager (Andrew Atkinson) to implement |