Date | Responsibility | Deliverables |
---|---|---|
|
Authoring begins for the July 2019 International Edition editing cycle. | |
|
Content team to deliver final MRCM change requests to EPS Team for action |
|
|
EPS Team delivers MRCM changes to content team for review - Content Team to complete this by |
|
|
Content team to deliver final reviewed MRCM changes plus any feedback to EPS Team |
|
|
EPS Team to make any necessary changes (based on feedback from the authors) and verify with Content Team by |
|
|
Jane Millar | Cut off for external collaboration partner CRS Requests (IHE, HL7, etc) - set date of 15th March + 15th September each cycle for clarity |
|
NO FURTHER MRCM CHANGES ACCEPTED - everyone has agreed this, with the caveat that any critical changes can be reviewed by all of us in order to analyse impact vs business case and allow a change if absolutely necessary. | |
|
Final MRMC refsets delivered by EPS Team to Release Management team for review |
|
|
SNOMED International Tech Team to now:
|
|
|
NO FURTHER CRS REQUESTS ACCEPTED (Single content request cut off) |
|
|
|
|
|
|
|
|
Content team review, rebase and finalise all content |
|
|
Content team promote to MAIN final content for all projects to be released in the current editing cycle (weekend contingency) |
|
|
Content Release Lead to request (via Infra ticket) formal lock down of all Projects (i.e. no promotions allowed), except for the Internal QA Project - which needs to remain open until from CONTENT CUTOFF DATE in order to allow Content Release Lead to promote all final QA fixes before handover. |
|
|
Final content review (2 days - BEWARE OF BANK HOLIDAY ON 6th May 2019!) Review of new observable entity and evaluation procedure concepts for conflicts with the LOINC agreement |
|
|
|
|
|
Planned Initial Handover meeting |
|
|
|
|
|
Transition from Stated Relationships to OWL refsets + Validation of the new complete OWL refsets |
|
|
termServer branching and Release versioning |
|
|
Andrew Atkinson | Full validation of the initial exported content, including the new OWL refsets |
|
|
|
|
|
|
|
|
|
|
|
|
|
Handover of Release Notes to technical team Release manager |
|
|
PLANNED Alpha Release date Restart validation in SCA (no longer relevant - new process should allow validation to re-start immediately when Content authoring starts for next editing cycle) |
|
|
PLANNED Alpha feedback deadline |
|
|
PLANNED BETA Release date |
|
|
PLANNED BETA feedback deadline | |
|
Member Release date |
|
|
Public Release date |