Date | Responsibility | Deliverables | |||
---|---|---|---|---|---|
| Authoring begins for the July 2019 International Edition editing cycle. | ||||
| Content team to deliver final MRCM change requests to EPS Team for action | ||||
| EPS Team delivers MRCM changes to content team for review - Content Team to complete this by | ||||
| Content team to deliver final reviewed MRCM changes plus any feedback to EPS Team | ||||
| EPS Team to make any necessary changes (based on feedback from the authors) and verify with Content Team by | ||||
| NO FURTHER MRCM CHANGES ACCEPTED - everyone has agreed this, with the caveat that any critical changes can be reviewed by all of us in order to analyse impact vs business case and allow a change if absolutely necessary. | ||||
| Final MRMC refsets delivered by EPS Team to Release Management team for review | ||||
| MRCM updated in the SCA to ensure remaining new cycle content validated against the latest version. |
| SNOMED International DevelopmentTech Team to now:
| ||
| NO FURTHER CRS REQUESTS ACCEPTED (Single content request cut off) | ||||
|
| ||||
|
| ||||
| Content team review, rebase and finalise all content | ||||
| Content team promote to MAIN final content for all projects to be released in the current editing cycle (weekend contingency) | ||||
| Content Release Lead to request (via Infra ticket) formal lock down of all Projects (i.e. no promotions allowed), except for the Internal QA Project - which needs to remain open until from CONTENT CUTOFF DATE in order to allow Content Release Lead to promote all final QA fixes before handover. | ||||
| Final content review (2 days - BEWARE OF BANK HOLIDAY ON 6th May 2019!) Review of new observable entity and evaluation procedure concepts for conflicts with the LOINC agreement | ||||
|
| ||||
| Planned Initial Handover meeting | ||||
|
| ||||
| Transition from Stated Relationships to OWL refsets + Validation of the new complete OWL refsets | ||||
| termServer branching and Release versioning | ||||
| Andrew Atkinson | Full validation of the initial exported content, including the new OWL refsets | |||
|
| ||||
|
| ||||
|
| ||||
|
| ||||
Handover of Release Notes to technical team Release manager | |||||
| PLANNED Alpha Release date Restart validation in SCA | ||||
| PLANNED Alpha feedback deadline | ||||
| PLANNED BETA Release date | ||||
| PLANNED BETA feedback deadline | ||||
| Member Release date | ||||
| Public Release date |
...