Date | Deliverables |
---|---|
| Authoring begins for the July 2019 International Edition editing cycle. |
| Content team (Yongsheng Gao) to deliver final MRCM change requests to EPS Team (Linda Bird) for action |
| Linda Bird delivers MRCM changes to content team for review - Content Team to complete this by |
| Content team (Yongsheng Gao) to deliver final reviewed MRCM changes plus any feedback to Linda Bird |
| Linda Bird to make any necessary changes (based on feedback from the authors) - Linda Bird to complete this (and verify with Yongsheng Gao) by |
| NO FURTHER MRCM CHANGES ACCEPTED - everyone has agreed this, with the caveat that any critical changes can be reviewed by all of us in order to analyse impact vs business case and allow a change if absolutely necessary. |
|
|
|
|
12 |
|
|
|
| Content team review, rebase and finalise all content (Maria Braithwaite to manage) |
| Content team promote to MAIN final content for all projects to be released in the current editing cycle (weekend contingency) - Maria Braithwaite to confirm |
| Content Release Lead (Maria Braithwaite) to request (via Infra ticket) formal lock down of all Projects (i.e. no promotions allowed), except for the Internal QA Project - which needs to remain open until from CONTENT CUTOFF DATE in order to allow Content Release Lead to promote all final QA fixes before handover. |
| Final content review (2 days) - Content Release Lead (Maria Braithwaite) to action Review of new observable entity and evaluation procedure concepts for conflicts with the LOINC agreement (Farzaneh Ashrafi Suzanne Santamaria) |
|
|
|
|
|
|
|
|
|
|
Handover of Release Notes to technical team Release manager (Andrew Atkinson) | |
| PLANNED Alpha Release date |
| PLANNED Alpha feedback deadline |
| PLANNED BETA Release date |
| PLANNED BETA feedback deadline |
| Member Release date |
| Public Release date |
...