Authoring begins for the July 2019 International Edition editing cycle.
Content team (Yongsheng Gao) to deliver final MRCM change requests to EPS Team (Linda Bird) for action
Linda Bird delivers MRCM changes to content team for review - Content Team to complete this by
Content team to deliver final reviewed MRCM changes plus any feedback to Linda Bird
Linda Bird to make any necessary changes (based on feedback from the authors) - Linda Bird to complete this (and verify with Yongsheng Gao) by
NO FURTHER MRCM CHANGES ACCEPTED - everyone has agreed this, with the caveat that any critical changes can be reviewed by all of us in order to analyse impact vs business case and allow a change if absolutely necessary.
Final MRMC refsets delivered by Linda Bird to Release Management team for review +
MRCM updated in the SCA to ensure remaining new cycle content validated against the latest version.
SNOMED International Development Team (Kai Kewley) to now add UUIDs to the MRCM google sheet for all new MRCM rules.
NO FURTHER CRS REQUESTS ACCEPTED (Single content request cut off), +
NO FURTHER BATCH REQUESTS TO BE IMPORTED - EITHER FROM CRS OR IMPORT/SCRIPT LOAD TO SCA (however, this should be earlier for huge or complex batches)
NO FURTHER DRUGS BATCH LOADS TO termServer
NO FURTHER PROMOTION FOR PROJECTS THAT HAVE LARGE SCALE CHANGES - For example this would include large scale changes to foundational hierarchies such as anatomy or substances, or changes that are likely to have impact to reports such as the pattern report (e.g. redundant relationships) or MRCM (e.g. cardinality issues in legacy content where edits have been made to that content without resolving the pre-existing cardinality issue).
Early Visibility Handover meeting (if complexity of Release requires), +
Last day for authors to launch new tasks in SCA - no more new tasks launched after this date
Content team review, rebase and finalise all content (Maria Braithwaite to manage)
Content team promote to MAIN final content for all projects to be released in the current editing cycle (weekend contingency) - Maria Braithwaite to confirm
Content Release Lead (Maria Braithwaite) to request (via Infra ticket) formal lock down of all Projects (i.e. no promotions allowed), except for the Internal QA Project - which needs to remain open until from CONTENT CUTOFF DATE in order to allow Content Release Lead to promote all final QA fixes before handover.
Final content review (2 days) - Content Release Lead (Maria Braithwaite) to action
Review of new observable entity and evaluation procedure concepts for conflicts with the LOINC agreement.
CONTENT CUTOFF DATE (12:00 UTC), +
Planned Initial Handover meeting, +
Handover of content to technical team Release manager (Andrew Atkinson)
termServer branching and Release versioning - SNOMED International Development Team, +
Mapping Team (Donna Morgan) to notify WCI mapping/review ready for QA
Yongsheng Gao to confirm that Lateralizable refset is complete in Production refset tool, Andrew Atkinson to then do the release and get the delta files, +