Date of Initial Handover meeting: 7 November 2024
Date of Final Handover meeting: 12 November 2024
Attendees
- Andrew Atkinson (AAT)
- Maria Braithwaite (MBR)
- Donna Morgan (DMO)
- Joe Schofield(JSC)
- Chris Morris (CMO)
- Rick Wood (RWO)
Page properties | ||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Agenda
Items to be discussed | Actions | |||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Prerelease Content Management Activities:
|
| ||||||||||||||||
2 | Discussion of existing Known Issues | Tickets logged for December 2024 release: TRACEABILITY - MRCM CHANGES - None VALIDATION -
| ||||||||||||||||
3 | Content Validation
|
| ||||||||||||||||
4 | Mapping schedule | January 2024 release -
February 2024 release - One concept deleted after promotion 123131000119105 |Benign carcinoid tumor of transverse colon (disorder)| - created + deleted within same cycle, therefore shouldn't appear in Release at all
March 2024 release -
April 2024 release -
May 2024 release -
June 2024 Release -
July 2024 Release -
August 2024 Release-
September 2024 Release-
October 2024 Release-
November 2024 Release-
December 2024 Release-
| ||||||||||||||||
5 | Brief run through of the known issues already identified by the content team during the QA batch process, to ensure that technical team are aware of them, and can either resolve them in time for the release, or confirm as known issues. | |||||||||||||||||
6 | DevOps resource confirmed | |||||||||||||||||
7 | Versioning and Change Freeze | Plan is to follow the new processes as now defined: December 2024 International Edition Release Schedule - Production Monthly Release - INTERNAL ONLY | ||||||||||||||||
8 | Stats Report | Summary Component Stats Report | ||||||||||||||||
9 | Risks | Planned promotion of bulk update of Orphanet and AJCC attribution - Orphanet starting December release until complete, AJJC planned for Jan 2025 release. | ||||||||||||||||
10 | AOB |