Date | Responsibility | Deliverables | ||
---|---|---|---|---|
| Authoring begins for the January 2020 International Edition editing cycle. | |||
01 | Content team to deliver final MRCM change requests to EPS Team for action | |||
| EPS Team delivers MRCM changes to content team for review - Content Team to complete this by | |||
| Content team to deliver final reviewed MRCM changes plus any feedback to EPS Team | |||
| EPS Team to make any necessary changes (based on feedback from the authors) and verify with Content Team by | |||
| Jane Millar | Cut off for external collaboration partner CRS Requests (IHE, HL7, etc) - set date of 15th March + 15th September each cycle for clarity | ||
| NO FURTHER MRCM CHANGES ACCEPTED - everyone has agreed this, with the caveat that any critical changes can be reviewed by all of us in order to analyse impact vs business case and allow a change if absolutely necessary. | |||
| Final MRMC refsets delivered by EPS Team to Release Management team for review | |||
| SNOMED International Tech Team to now:
| |||
| NO FURTHER CRS REQUESTS ACCEPTED (Single content request cut off) | |||
|
| |||
|
| |||
| Content team review, rebase and finalise all content | |||
| Content team promote to MAIN final content for all projects to be released in the current editing cycle (weekend contingency) | |||
| Content Release Lead to request (via Infra ticket) formal lock down of all Projects (i.e. no promotions allowed), except for the Internal QA Project - which needs to remain open until from CONTENT CUTOFF DATE in order to allow Content Release Lead to promote all final QA fixes before handover. | |||
| Final content review (2 days) Review of new observable entity and evaluation procedure concepts for conflicts with the LOINC agreement | |||
|
| |||
| Planned Initial Handover meeting *** Maria to cover whilst Andrew is away | |||
|
| |||
| termServer branching and Release versioning | |||
| Andrew Atkinson | Full validation of the initial exported content (to be done during last week of October due to annual leave in November this year) | ||
|
| |||
|
| |||
|
| |||
Handover of Release Notes to technical team Release manager | ||||
|
| |||
15 | Maria BraithwaiteHandover of Release Notes to technical team Release manager |
| PLANNED Alpha Release date Restart validation in SCA (no longer relevant - new process should allow validation to re-start immediately when Content authoring starts for next editing cycle) | |
29 Nov | PLANNED Alpha feedback deadline | |||
04 | PLANNED BETA Release date | |||
| PLANNED BETA feedback deadline | |||
| Member Release date | |||
| Public Release date |
...