Date | Responsibility | Deliverables | |
---|---|---|---|
| Authoring begins for the January 2020 International Edition editing cycle. | ||
01 | Content team to deliver final MRCM change requests to EPS Team for action | ||
| EPS Team delivers MRCM changes to content team for review - Content Team to complete this by 13 Mar | ||
| Content team to deliver final reviewed MRCM changes plus any feedback to EPS Team | ||
| EPS Team to make any necessary changes (based on feedback from the authors) and verify with Content Team by 15 Mar | ||
| Jane Millar | Cut off for external collaboration partner CRS Requests (IHE, HL7, etc) - set date of 15th March + 15th September each cycle for clarity | |
| NO FURTHER MRCM CHANGES ACCEPTED - everyone has agreed this, with the caveat that any critical changes can be reviewed by all of us in order to analyse impact vs business case and allow a change if absolutely necessary. | ||
| Final MRMC refsets delivered by EPS Team to Release Management team for review | ||
| SNOMED International Tech Team to now:
| ||
| NO FURTHER CRS REQUESTS ACCEPTED (Single content request cut off) | ||
|
| ||
|
| ||
| Content team review, rebase and finalise all content | ||
| Content team promote to MAIN final content for all projects to be released in the current editing cycle (weekend contingency) | ||
| Content Release Lead to request (via Infra ticket) formal lock down of all Projects (i.e. no promotions allowed), except for the Internal QA Project - which needs to remain open until from CONTENT CUTOFF DATE in order to allow Content Release Lead to promote all final QA fixes before handover. | ||
| Final content review (2 days - BEWARE OF BANK HOLIDAY ON 6th May 2019!) Review of new observable entity and evaluation procedure concepts for conflicts with the LOINC agreement | ||
|
| ||
08 May | Planned Initial Handover meeting *** Maria to cover whilst Andrew is away | ||
|
| ||
| termServer branching and Release versioning | ||
| Andrew Atkinson | Full validation of the initial exported content (to be done during last week of October due to annual leave in November this year) | |
|
| ||
|
| ||
|
| ||
Handover of Release Notes to technical team Release manager | |||
|
| ||
Handover of Release Notes to technical team Release manager | 20 | PLANNED Alpha Release date Restart validation in SCA (no longer relevant - new process should allow validation to re-start immediately when Content authoring starts for next editing cycle) | |
29 Nov | PLANNED Alpha feedback deadline | ||
04 | PLANNED BETA Release date | ||
| PLANNED BETA feedback deadline | ||
| Member Release date | ||
| Public Release date |
...